| Whiskeytown Logging Road Removal
Project Whiskeytown Project Home Page | The Cooperative Agreement | Why Remove Logging Roads? | Developing an Erosion Inventory for Road Decommissioning | Outsloping Peltier Valley Road | The Sediment Pond | Logging Camp Road Removal | Landing Removal | Conclusion | Erosion Inventory The key to cost-effective sediment reduction is prevention, not treatment
of what has already happened. Therefore, erosion inventories
must evaluate all existing and potential problems along roads and
The class developed inventory forms based on advice from Redwood National
Park’s Terry Spreiter and geologist Neal Youngblood.
The strategy used divided the inventory into two distinct areas;
the “site” which is where the road crossed a drainage,
and the “road segment” which is the road length in-between
sites. The road erosion inventory form therefore has two sections,
one for sites (swale or stream crossings), and one section for road
segments. As the teams proceeded down the road, the appropriate
section - either site or segment - was filled out. Photographs
were taken of each site or segment. Road condition, accessibility,
width, and length were also noted and recorded on the data sheet.
Data was collected for the sites, including the type of site, i.e., stream crossing, headwater swale crossing, spring, crossroad drain, or other. The amount of fill in the site was estimated as an order of magnitude ranging from small (1-5 m³) to extra-large (greater than 50 m³). Potential for future erosion was evaluated and recommended treatment(s) were suggested. Possible treatments included a shallow dip (10% of the fill removed), culvert replacement, a large dip (50% of the fill removed), or complete crossing removal (100% of the roadfill would be excavated). Justifications for the treatment recommendations were also recorded. Data was also collected for the road segments. The amount of fill in the road wedge was estimated in cubic yards, and the potential for future erosion was assessed as high, moderate, or low. Based on this information, a potential treatment was recommended, i.e., outslope, outslope with rolling dip, or recontour (partial or complete road removal). Estimates of potential erosion volume are by nature imprecise, inconsistent, and difficult because the numbers are calculated from estimates of dimensions of as yet unformed erosion features. Therefore, the dimensional numbers collected in the field are extremely subjective and should not be used as anything more than an indicator of the order of magnitude of what might occur in a major (50 year +) storm. The Watershed Restoration class looked at the disturbed lands, especially at the road and stream crossings (x-ings), and tried to determine the boundary between the fill and the undisturbed ground. The question asked was “Where was the road cut and where was it filled?”. The identification of fill versus native ground is not always obvious, thus the need for a strong geomorphic background. The amount of fill was put into relative categories, small (1-5 m³), medium (5-20 m³), large (20-50 m³), and extra-large (greater than 50 m³). The student teams used a unique technique to calibrate and visualize the amount of roadfill in channels. A “small” became a Volkswagon Bug, a van (the volume our college van would occupy) was a “medium”, a Greyhound Bus became synonymous with a “large” amount of fill, and finally an “extra-large was equated to the volume a triple-wide mobile home might occupy. The information collected was entered into a database and then linked to a geographic information system (GIS). The Shasta College Engineering and GIS students got involved at this point and GIS maps were developed (Figure 6). The attributes for each site and segment can now be queried with Arcinfo™. Even the “before” photographs have been digitized and entered into the database. This should prove to be an invaluable monitoring tool.
|